Industryweek 8574 Elephant
Industryweek 8574 Elephant
Industryweek 8574 Elephant
Industryweek 8574 Elephant
Industryweek 8574 Elephant

Taking a Bite Out of Lead Time

April 9, 2015
Value-stream mapping offers opportunities to reduce lead time by identifying the build-up of work-in-process (WIP) which exists between operations in a process.

How do you eat a chocolate elephant? Well, the answer is easy and well-known – one bite at a time. The same is true when nibbling away at reducing lead time. A value stream map identifies opportunities through the build-up of work-in-process (WIP) which exists between operations in a process.

The first step is to prioritize the series of operations which will yield the most significant results. Nothing ensures continuous improvement like early success, and the bigger the success, the more momentum a team will gain in working to gain further improvements.

There are two ways to determine lead time. The first is by checking actual performance, through reviewing transactional history from routers attached to the material. This should be done during the data gathering phase of the value stream mapping process. If routers aren’t used, then transactional history may be taken from the enterprise resource planning system’s material management module.

The second method, and perhaps even more revealing, is to calculate the lead time using Little’s Law. While on the data gathering walk of the VSM event, count the inventory at each operation. Then, use the simple formula. Little’s Law is simply expressed by dividing the amount of work-in-process by the daily requirement. The result yields the number of days of lead time.

EXAMPLE of Little’s Law:
100 pieces of WIP are queued. The daily requirement is to process 50 pieces. 100/50 means there is two days of lead time.

(Hint: Don’t mix methods! Use the actual days from routers or Little’s Law). Regardless of how the team arrives at the lead times, the work of the following kaizen events is to reduce lead times.

The kaizen team should regard every queue as the waste that it is. Work-in-process should not be arbitrarily reduced to zero. The technique is known as “lean,” not “anorexic.” The correct amount of work-in-process is calculated by dividing the operation’s total cycle time by takt time. This result yields “Standard Work-in-Process” (SWIP)

EXAMPLE of Standard Work-in Process calculation:
Total cycle time of an operation is 60 minutes – 20 minutes of unload and load, and 40 minutes of cutting time. Takt time is 80 minutes, so the SWIP would be .75, or 1 piece.

Now, the team must consider the current limitations to reducing current WIP to SWIP. There may be a lengthy change-over that’s not a SMED (single minute exchange of dies), but more like a shed (single HOUR exchange of dies). There may be staffing issues, which reveals the need for standard work combinations and effective cross-training. A more complex issue may be large equipment installations that preclude co-locating into a cell or process layout. Along with implementing improvements, visual controls must be put in place so there’s no ‘augmentation’ to the defined SWIP. And, any amounts of WIP in excess of WIP required by current process limitations remain targets for further kaizen.

Cutting Lead Time in Half

One of our clients had identified opportunities through a value stream mapping event. They divided the process into four major VSM planning loops, with a fifth loop focused on administrative (planning, forecasting and order receipt) activities. They saw opportunities with the final sequence of operations – two inspection operations, an assembly kitting operation and a final pack operation.

The material is lot-controlled, so the parts can maintain traceability through the entire product life-cycle – an important requirement in the industry they serve. Parts would pile up while inspectors were performing other duties – the symptom of large lot, batch method material movement. When orders became due, or overdue, then it was an all hands on deck call to hustle material through the operations and onto a plane to the customer. This approach chews up a lot of space, a potential quality issue with mixed lot materials, and creates pressure to get stuff out the door almost at any cost.

Did we mention air-freight and overtime costs? The team used the Little’s Law approach to calculate lead time – 10.5 days of WIP. The sum of all operations’ cycle times was 10 minutes, which is about one minute of work per day per piece (not a great example of material flow!).

They calculated standard work-in-process, which worked out to be 2. They decided that for each of two different products (size and number of pieces per assembly set), it would be best to establish two inspection cells, facilitating flow for each product. Then the SWIP was reduced to 1 for each cell! As the parts were inspected, kitted (left and right for the large parts; left, right and center for the smaller parts), and bagged, they were placed on a cart bound for pack. When the SWIP was reached – indicated by the filling of the rack on the cart ­ it was wheeled out of the clean room to a packing station where the inspector would final pack the parts, print the label, and call for pick up from shipping. They would then return to the clean room to commence inspecting the next group of parts.

While it would be a perfect ending to say this ended the air freight, it did not, at least right away. When there was enough in the supply chain, the company was able to start shipping by truck, so that air freight is an occasional charge, not a daily expense.

The total cost of the improvements was about $500 – a cart, some racks, and some colored tape. Lead time was 10.5 days and is now 5 days. The team stays focused on further improvements to reduce the WIP to SWIP, which would result in a 2 day lead time.

Chocolate elephant? Not completely eaten, but it’s lost some weight!

Daniel Penn Associates, LLC Senior Consultant Tom Voss has developed and implemented lean enterprise solutions for more than 15 years. His experience spans chemical, industrial, aerospace, automotive and telecommunications industries as well as insurance, banking and public sector services. Questions or comments: contact [email protected] or call 860-232-8577.

Popular Sponsored Recommendations

Discrete and Process Manufacturing 2024 Trends and Outlook for North America

March 5, 2024
We surveyed over 200 discrete and process manufacturers to give you an idea of what sets thriving manufacturers apart from the rest, as well as which strategies are most effective...

Top 3 Ways AI is Transforming Manufacturing Operations

Feb. 17, 2024
Unlock the power of Industry 4.0 with AI and IoT. Explore how real-time data and automation are reshaping manufacturing, driving efficiency and quality to new heights. Dive into...

Low-Volume Rapid Injection Molding With 3D Printed Molds

Oct. 18, 2022
This white paper provides methods and guidelines for using stereolithography (SLA) 3D printed molds in the injection molding process to lower costs and lead time.

Food and Beverage 2024 Trends and Outlook for North America

Oct. 29, 2023
Ready to hear what 200 of your peers said are the top challenges and opportunities in 2024? Don’t fall behind. Uncover actionable insights to better prepare for 2024 in this whitepaper...

Voice your opinion!

To join the conversation, and become an exclusive member of IndustryWeek, create an account today!