Image

How to Sustain Your Lean Equipment Maintenance Program

Aug. 7, 2015
Twelve tips for minimizing unplanned downtime through proper preventive maintenance.

“Asset utilization, also called Overall Equipment Effectiveness (OEE) or equipment capacity, is not just the responsibility of one department. It is the responsibility of the entire company. It has the focus of ensuring that nowhere in the world does another company have the same assets or produces greater capacity from those assets. It means being the best at getting the most out of the assets by measuring and managing availability, performance efficiency, and quality rate.” – Terry Wireman, author, Zero Breakdown Strategies

Overall equipment effectiveness (OEE). Total productive maintenance (TPM). Reliability Centered Maintenance (RCM). The guidelines are not new. But for companies that truly want to maximize their equipment uptime, productivity and quality, a disciplined approach is critical. So is creating a culture where everyone understands and carries out their role in the maintenance continuum.

Situation 1:

A machine shop decided to adopt the TPM approach to proactively care for their large machines. They trained the maintenance team to implement the program for key equipment. The team developed a “war wagon” with all the tools, critical parts and chemicals to perform scheduled maintenance and emergency repairs on machines throughout the facility.

However, the wagon wasn’t maintained, so when mechanics went on a call, components hadn’t been restocked. Tooling was missing. Chemical supplies dropped to low levels or were completely exhausted. Because the maintenance store was disorganized, restocking the wagon took longer. Frustrated, the maintenance team took matters into their own hands, dedicating one wagon to unplanned machine stoppages and another to planned maintenance efforts.

Situation 2:

A chemical processing facility we visited had more motors in their maintenance stock room than the plant had in service. More than half of the motors and several electronic control components in stock were for equipment the company no longer owned. And because the right spares for current equipment were not on hand, unscheduled downtime stretched into weeks.

Certainly, maintenance priorities in a heavy machining plant will be different from an assembly plant or a chemical processing plant. Regardless, these practices can be applied across most production facilities:

1. Borrow from successful lean production techniques and process map your maintenance workflow. The Marshall Institute recommends beginning the mapping effort at the very beginning of your maintenance process and the flow of the process from one step to the next. Once the map is done, you’ll see and eliminate as many of these extra maintenance steps as possible.

A good 5S program results in better housekeeping but its main purpose is to offer a process for identifying, solving and preventing problems.

see areas for improvement. Depending 

on your facility, industry and specific needs, the use of 5S techniques can be important tools to help you identify problems in the maintenance process.

3. Depending on your industry and facility needs, consider Single Minute Exchange of Dies (SMED) strategies to reduce machine changeover times, reduce labor and meet just-in-time production goals. Nanoplas Inc., a producer of plastic mold coatings, greases, lubricants, cleaners and corrosion control products, recently wrote about how it successfully uses SMED for its injection-molding processes.

4. Give machine operators process ownership.  According to a recent blog post in Paper Advance, the Canadian pulp-and-paper industry’s trade resource, a number of real-time digital condition monitoring and reporting systems now support the positive trend to operator-driven reliability (ODR). The Total Productive Maintenance (TPM) approach shifts basic maintenance work (and problem notification) to machine operators, freeing up maintenance personnel to work on planned maintenance. The idea is to give workers ownership of their machine and the process, maximize equipment effectiveness, increase employees’ skills and reduce manufacturing costs through continuous monitoring. For their part, the maintenance team should respond to requests within a pre-determined time window.

5. Schedule your facility’s planned maintenance program far in advance, just as any other operation, to maximize productivity and meet order deadlines. Annual checks are going to be more comprehensive than a monthly or quarterly check, meaning the machine will be down for longer, so make sure they synch with your production commitments.

6. Use your ERP system to plan for downtime, just as it does for jobs. The ERP ties in with the procurement function, and if properly described with consumption amounts and order lead times, maintenance parts will have been ordered in advance and arrive at your plant in time for the machine to be serviced. Use your ERP or CMMS system to specify the maintenance mechanic who will work on the machine, and to specify the parts and chemicals needed to complete the maintenance activity.

7. Schedule more frequent checks for older equipment. As equipment ages, parts and components will start to wear out sooner, and the maintenance window narrows. What were annual checks when the equipment was new may move to semi-annual or even monthly. The service parts required will have to be ordered more often. However, the planned downtime will affect production schedules less than a breakdown.

8. Engineer machine improvements for maintainability and operability. Windows cut into guarding to give easier viewing of gauges will make the daily checks easier to perform and more likely to be completed. Access doors installed on equipment will allow for easier periodic maintenance. Consolidation of lubrication points into a single manifold also contributes to more consistently performed maintenance.

9. Conduct daily operator walk-arounds to pinpoint issues and opportunities for improvement. Whether it’s a check sheet, whiteboard or, in some cases, a bar-coded activity, the operator’s checks are the essential element of a TPM-oriented operation.

10. Address operator alerts immediately. Beyond the operator and the proper performance of the checks, the maintenance organization must be ready to respond immediately to an abnormality that’s been raised as part of the operator checks. Nothing will take the energy of TPM efforts faster than operators raising issues that aren’t addressed immediately.

11. Continually review spare part requirements. Remove any spare parts from stock as equipment and machines are retired.

12. Document and continually re-visit your operation’s maintenance history, including how critical items have addressed. Develop and regularly review metrics that correlate equipment up and down time with production volume, quality and delivery.

Whether you use a computer-based maintenance system, or you rely on a card file, or you have a white board in the maintenance area, the strategies, opportunities and approaches remain the same. Once implemented, the entire workforce – from senior management all the way down to the last mechanic hired, must adhere to the basic tenet: minimize unplanned downtime through proper preventive maintenance.

Antonio (Tony) Rodriguez, CMC, president of Daniel Penn Associates, LLC, is a certified management consultant with 35 years experience in encouraging collaboration and progressive thinking to bring about organizational change. With expertise in facilitation/team development, Lean Six Sigma, re-engineering and supply chain optimization, supplier diversity, strategic sourcing, asset management and productivity improvement, Rodriguez directs projects for public and private organizations in the U.S. and globally.

Daniel Penn Associates, LLC Senior Consultant Tom Voss has developed and implemented lean enterprise solutions for more than 15 years. Trained and mentored in Lean concepts by the founders of Shingijitsu Company, Ltd., his experience spans chemical, industrial, aerospace, automotive and telecommunications industries as well as insurance, banking and public sector services. Questions or comments? Write them at [email protected] or call 860-232-8577.

Sponsored Recommendations

Voice your opinion!

To join the conversation, and become an exclusive member of IndustryWeek, create an account today!